Act on the Obwalden Electricity Works and Electricity Supply (EWOG) - Legal Form (EWOG)
Table of Provisions (33)
Statutory Text (33 Articles)
1. The Obwalden Electricity Works (hereinafter referred to as "EWO") is a public-law institution with its own legal personality and is based in Kerns.
**1. The Public Mandate of the EWO Comprises:**
a. the safe, economical, and environmentally-friendly supply of electrical energy in the Canton of Obwalden;
b. the promotion of efficient energy use and the deployment of renewable energy within the framework of market-based services.
1. The EWO
a. * generates electrical energy through the construction and operation of its own power plants and can participate in production companies;
b. * ensures the supply of electrical energy within the allocated network areas;
c. procures, sells, and exchanges electrical energy;
d. promotes the use of renewable energy sources;
e. informs and advises on issues of electricity supply and application.
2. The EWO can furthermore, in particular
a. prepare and distribute energy from combined heat and power plants, wood chip, and other energy generation facilities;
b. make its own network available for telecommunications and other related services;
c. engage in the installation business.
3. The EWO can also operate outside the cantonal area. It is further entitled to perform all activities that are directly or indirectly related to its tasks. For this purpose, it can participate in public or private law enterprises and transfer business areas according to paragraph 2 as well as transregional distribution systems into legally independent units.
1. The EWO is to be managed in accordance with recognized commercial and business management principles. The results of the individual business sectors are to be reported separately.
2. The EWO should generate a profit appropriate to the capital employed.
1. The endowment capital of the EWO amounts to 7.5 million Swiss Francs, in which the canton holds an eight-fifteenths share, and each of the seven municipalities holds a one-fifteenth share.
2. The EWO must provide an appropriate return on the endowment capital. The risk associated with the capital must be reflected in the interest rate.
3. The endowment capital can be increased for the fulfillment of the EWO's tasks through a cantonal council resolution, upon proposal by the board of directors. The municipalities may participate in the increase in the original proportion.
1. The Cantonal Council
a. exercises supreme supervision;
b. * annually approves the business report and financial statements, and grants discharge to the bodies of EWO;
c. approves participations exceeding eight million Swiss francs, and new investments exceeding 20 million Swiss francs;
d. * decides on changes to the endowment capital after consulting with the municipalities;
e. * acknowledges the owner's strategy, including any future changes thereto.
1. The Executive Council
a. * exercises supervision over the EWO and regulates the modalities;
a1. * establishes, within the framework of the ownership strategy, the entrepreneurial, economic, and political objectives of the canton and the municipalities as owners, in conjunction with the other owners, as well as the guidelines for management, control, efficiency, and transparency, reviews these periodically, and makes necessary adjustments as needed;
b. regulates the modalities for the election and removal of the Board of Directors; appoints the members and the presidency for a term of four years and approves their remuneration;
c. appoints the auditing body;
d. * annually reviews the management report and, based on the audit report, the annual financial statements of the EWO and the companies in which the EWO holds a majority interest, and submits a proposal to the Cantonal Council;
e. can initiate clarification of special issues;
f. * ...
g. determines conclusively the interest rate and the specifics of the interest on the endowment capital;
h.-i. * ...
1. The bodies of the EWO are
a. the Board of Directors;
b. the Executive Management;
c. the Audit Office.
1. The Board of Directors consists of five to seven members. The municipal councils and the Board of Directors have the right to make proposals.
1. The Board of Directors manages the affairs of the EWO, unless it has delegated the management or if another cantonal authority is responsible according to this law.
2. It has the following non-transferable and inalienable duties
a. to exercise the overall management of the EWO and to issue the necessary directives;
b. to define the organization of the EWO and to adopt organizational regulations;
c. to structure the accounting and financial control as well as to establish the financial planning;
d. to appoint and dismiss the persons entrusted with management (executive management) and representation;
e. to exercise the overall supervision over the persons entrusted with management, specifically regarding the compliance with laws, regulations, and directives;
f. to prepare the annual report and to submit proposals in matters to be decided by the Government Council according to Art. 10 letters a1, b, c, and d as well as g of this law;
g. to determine the general employment conditions of the staff based on the Code of Obligations;
h. to establish the fiscal year;
i. to commission third parties with the provision of services;
k. to set and publish the electricity tariffs and network usage tariffs.
2a. The Board of Directors carries out its activities in accordance with the owner's strategy as per Art. 10 letter a1 of this law.
3. In all other respects, the provisions of Art. 716a et seq. of the Code of Obligations apply mutatis mutandis.
1. The Executive Management is the operational management body of the EWO. Its position, tasks, and powers are specifically determined by the Board of Directors in the Organizational Regulations.
1. The audit office must correspondingly fulfill the qualification requirements according to Art. 727a et seq. of the Swiss Code of Obligations. It annually audits the accounts according to statutory provisions and recognized Swiss auditing standards.
2. It reports to the Board of Directors and submits motions for the attention of the government council.
1. The duty of care and loyalty outlined in Art. 717 para. 1 and Art. 728 ff. of the Swiss Code of Obligations applies mutatis mutandis to the members of the Board of Directors and the Executive Board as well as the audit firm.
2. Data protection is governed mutatis mutandis by the provisions of the State Administration Act.
1. For liabilities and damage caused to third parties, only the EWO is liable with its own assets.
2. The members of the Board of Directors, the Executive Management, and the Audit Office are liable to the EWO, as well as to the canton and the municipalities, for the damage they cause through culpable breach of their duty of care. The Liability Act is decisive for liability arising from official activities.
1. The canton and municipalities, as well as other public-law corporations and institutions, are obliged to provide the EWO with their public land, which is in common use, for distribution networks free of charge.
2. The EWO's ownership of distribution lines extends up to the connection overcurrent interrupter, even if the line runs over private land.
3. The route of the lines shall be recorded in the geoinformation system.
1. Existing claims of independent producers or rights to existing conduits and facilities, granted under issued concessions or acquired water rights, shall be preserved.
1. In setting electricity tariffs, the federal legal requirements according to the Federal Electricity Supply Legislation are decisive. In this context, for the energy to be supplied within the canton, consideration must be given to the long-term viability of the company, its investment needs, the interests of the population, and economic development.
2. Legal relationships with customers and third parties are governed by private law. To the extent that the Energy Supply Organization (EWO) performs tasks in accordance with Art. 22a ff. of this law, public law regulations apply.
1. The distributable portion of the net profit is determined according to the amount of the endowment capital and is guided by the provisions of the ownership strategy, which includes an arrangement between the canton, the municipal communities, and the EWO regarding the amount of the distributable portion of the net profit.
1. The EWO is not required to pay state and municipal taxes.
1. The Government Council decides on the allocation of the network areas. Prior to making a decision, it must hear from the network owners, network operators, and municipalities.
1. The allocation of network areas must cover the entire territory of the canton comprehensively.
2. The network areas are designated for network level 7. For network levels 3 and 5, a network area assignment must occur if a future need is foreseeable.
3. In the allocation of network areas, the government council must
a. consider, as far as possible, existing ownership relations of the electricity networks as well as existing contractual relations concerning the construction, operation, and maintenance of the electricity networks;
b. generally avoid dividing existing network areas, although exceptions are permissible for special reasons;
c. ensure an equal, transparent, and non-discriminatory allocation of network areas;
d. guarantee a safe, efficient, and cost-effective electricity supply.
1. If a network owner does not operate the network themselves, they must tolerate all measures taken by the network operator that serve to fulfill the basic supply, supply security, and service mandates pursuant to Article 22e of this law.
2. All network owners and network operators are required to immediately report to the Department of Construction and Spatial Development any relevant changes related to the operation and ownership.
1. Following the initial allocation of network areas, the Government Council shall make adjustments to the allocation of network areas based on an application from a network operator, a notification in accordance with Art. 22c para. 2 of this law, or ex officio.
2. The Government Council may revoke the allocation of a specific network area, in whole or in part, without compensation if
a. the network operator submits a corresponding application;
b. the supply is no longer guaranteed;
c. legal provisions or important ancillary provisions in connection with the allocation of a network area or with the service mandate are violated despite the setting of a grace period.
1. The Government Council may issue a service mandate to network operators, particularly for
a. ensuring basic supply;
b. ensuring supply security in the network sector;
c. increasing energy efficiency;
d. providing energy services.
2. When issuing service mandates, it is important to avoid competitive distortions among network operators.
1. Within the network area assigned to them, only the designated network operator is obligated to ensure the network connection.
2. The government council can obligate network operators to connect end consumers outside of building zones, who are not required to be connected under federal law, to their network, provided that
a. the connection costs for the end consumer are disproportionately high;
b. self-supply is not reasonable for the end consumer;
c. the connection is technically and operationally feasible and economically reasonable for the network operator.
3. The costs for the connection to the network are generally to be borne by the end consumers outside the building zone.
4. Deviating cost regulations are permissible within the framework of federal law provisions, provided that the contributions of the end consumers do not exceed the actual costs. If the parties cannot agree on the cost allocation, the Department of Construction and Spatial Development will decide.
5. The regulation of the Federal Energy Legislation applies to the connection costs of electricity producers.
1. The governing council may require network operators to connect end consumers to their network even outside of their network area if
a. supply is not possible or economically reasonable by other means;
b. the connection is technically and operationally feasible as well as economically viable for the network operator.
2. To the extent of the obligation of the new network operator, the previous network operator shall be released from the duty to connect.
1. The Government Council, after prior consultation with the municipalities and network operators and within the scope of its competencies, shall take measures to reconcile disproportionate differences in network usage tariffs within the canton.
1. Intentional violations of reporting and connection obligations, as well as the non-fulfillment of service orders, are punishable by a fine of up to CHF 100,000.
2. If the perpetrator acts negligently, the fine amounts to up to CHF 20,000.
3. Attempt and complicity are punishable.
4. Instead of a legal entity or partnership, the natural persons who acted or should have acted for the former are punishable. If these cannot be determined without disproportionate investigative effort, the legal entity or partnership is sentenced to pay the fine.
5. Jurisdiction and procedure are governed by the Swiss Code of Criminal Procedure.
1. The Government Council is authorized to take all preparatory actions and measures that are incumbent upon it under Article 10 of this Act, in order to enable the timely implementation of this Act. Where bodies are required to submit applications under this Act, the Government Council may rely on the applications of the previously designated bodies of the EWO.
2. Until new regulations are enacted or new agreements are concluded, the existing legal relationships with third parties shall continue to apply in accordance with the previous provisions and agreements.
3. The Government Council may issue additional transitional provisions to ensure a smooth transition.
1. Applications pending at the time this law comes into force shall be assessed according to the new law.
1. The Executive Council issues the implementing provisions required for execution.
2. In the implementing provisions, it may, in particular, declare the industry guidelines and professional standards as applicable.
1. The following are repealed
a. the Law on the Obwalden Power Plant dated November 29, 1981;
b. the Regulation on the Obwalden Power Plant dated December 18, 1981;
c. the Cantonal Council Resolution on the Increase of the Endowment Capital of the Obwalden Power Plant dated November 13, 1992.
1. This law shall enter into force on January 1, 2005, subject to the adoption of the constitutional amendment (restructuring of the Obwalden power plant).
2. Articles 10 and 22 shall enter into force immediately upon the legal validity of this law.
3. This law is subject to an optional referendum.