Art. 151 PBG · Interruption of Construction Work

1. The building authority may fully or partially revoke a construction permit if the construction work is halted for more than one year or is not seriously continued.

2. It simultaneously issues appropriate orders.

← Art. 150 PBG - Reporting Obligation and Construction Inspection Planning and Construction Act (PBG) - Local Planning Art. 152 APA →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

B.2023.176 · sg (Art. 151 PBG)
Building Permit Validity and Projection Interpretation in Construction Modification Case
Cited in the reasoning regarding the possibility of the building authority revoking a permit if construction ceases, confirming that no revocation occurred, thus preserving the permit's validity.