Court allows fee reduction to zero when statutory processing time is exceeded by over five weeks.

Numéro de cause P 713-25
Autorité / Tribunal
Juridiction Suède (SE)
Date de la décision
Issue du litige Admis (Allowed)

Synthèse Legislator

Généré par l'IA

The Administrative Court of Sweden reduced the building permit fee to zero because the statutory processing deadline in the Planning and Building Act was exceeded by more than five weeks. The applicant argued that the delay justified a full waiver of the fee, while the authority initially refused the reduction. The court ruled in favor of the applicant, holding that the statutory time limit must be strictly observed to ensure fair administrative treatment.

Regeste Legislator

Généré par l'IA

9 kap. 27 § plan- och bygglagen; When the statutory processing time limit is exceeded by more than five weeks, the building permit fee must be reduced to zero.

Mots-clés

Généré par l'IA
building permit fee statutory processing time Planning and Building Act administrative delay fee reduction processing deadline public administration prolongation du permis de construire

Dispositions légales citées

Généré par l'IA
9 kap. 27 § plan- och bygglagen
MÖD har reducerat en bygglovsavgift till noll kr då den lagstadgade handläggningsfristen i 9 kap. 27 § plan- och bygglagen överskridits med mer än fem veckor.
Généré par l'IA

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

MÖD har reducerat en bygglovsavgift till noll kr då den lagstadgade handläggningsfristen i 9 kap. 27 § plan- och bygglagen överskridits med mer än fem veckor.