Généré par l'IAThe Mark- och miljööverdomstolen (MMOD) permitted the construction of a sluice gate following the removal of a dam. The applicant argued the project violated environmental protections, while the opposing party contended it was necessary for water management. The court ruled that the specific measures fall within the scope of the relevant chapter of the Environmental Code, allowing the project to proceed.
Regeste Legislator
Généré par l'IA11 kap. 19 § miljöbalken; The construction of a sluice gate after dam removal is permissible if it complies with the specific requirements and procedures outlined in the designated chapter of the Environmental Code.
Mots-clés
Généré par l'IADispositions légales citées
Généré par l'IADécisions connexes
Généré par l'IATexte complet
MÖD har ansett att anläggandet av en sjötröskel med anledning av en utrivning av en damm är möjlig att pröva inom ramen för 11 kap. 19 § miljöbalken och har återförvisat målet till MMD, som avvisat ansökan, för fortsatt handläggning.