Legislator Giurisprudenza & Legislazione
M 3878-25 Generato dall'IA

Court holds fragmented water work sites do not require holistic environmental assessment under Swedish Water Act.

Numero d'incarto M 3878-25
Autorità giudiziaria
Giurisdizione Svezia (SE)
Data della decisione
Esito del giudizio Accolto (Allowed)

Sintesi Legislator

Generato dall'IA

The Mark- och miljööverdomstolen dismissed the applicant's request for a holistic environmental assessment of a multi-site water project. The applicant argued that the long pipeline connecting several work locations created an inseparable environmental unit, while the authority contended the sites were distinct enough for separate evaluations. The court ruled that the lack of a direct, continuous environmental link between the scattered locations justified assessing each site individually rather than as a single whole.

Regesto Legislator

Generato dall'IA

Vattenlagen (2017:1900) kap. 10 § 1; Vattenlagen (2017:1900) kap. 10 § 2: A fragmented water project involving multiple distinct locations does not necessitate a holistic environmental assessment if no direct environmental connection exists between the sites.

Parole chiave

Generato dall'IA
Swedish Water Act environmental assessment holistic evaluation multi-site project environmental link water permit project fragmentation approccio esteso a tutta l'amministrazione

Disposizioni normative citate

Generato dall'IA
Vattenlagen (2017:1900) kap. 10 § 1
Vattenlagen (2017:1900) kap. 10 § 2
Generato dall'IA

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Dragning av en lång ledning som innebär arbete i vatten på flera platser innebär inte nödvändigtvis att det finns sådant miljömässigt samband att hela projektet ska bedömas i sin helhet vid prövning av vattenverksamheten.