Recycling center deemed not to be limited environmental impact activity under current detailed plan.
Sintesi Legislator
Generato dall'IAThe Mark- och miljööverdomstolen dismissed the application regarding the environmental impact assessment of a recycling center. The applicant argued the facility constituted a limited environmental impact activity permitted by the existing detailed plan, while the opposing party contended it exceeded these limits. The court ruled that the specific nature of the recycling center did not qualify as such an activity under the current planning regulations.
Regesto Legislator
Generato dall'IASFS 1997:713, 1 kap. 10 a §; SFS 1997:713, 1 kap. 10 b §: A recycling center is not classified as an activity with limited environmental impact if its scale and operations exceed the thresholds defined in the current detailed plan.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IADecisioni correlate
Generato dall'IATesto completo
En återvinningscentral ansågs inte vara sådan verksamhet med begränsad omgivningspåverkan som medgavs i gällande detaljplan.